Known for their innovation in providing solutions to complex construction and have a reputation for delivering the highest quality of works in a professional and efficient manner.

Ethicon Sirenia Project Phase 1 - Janssen Ortho LLC - Manati Operations

LOCATION:

Manati, Puerto Rico

CLIENT:

CIC

SERVICES:

HVAC, Mechanical, Electrical, Plumbing

SUMMARY:

Under construction

STATUS:

Ongoing

DURATION:

9 months

This project consists of demolition & construction of a new cleanroom. All existing mechanical & electrical utilities are going to be demolished. We self-performed all electrical, mechanical works, & plumbing work. The installation of new MCC, panelboards, lighting fixtures, power & special systems rough-in are part of our scope. Also, the installation of AHU’s chilled water pipes, steam pipes, compressed air, vacuum system; equipment such as heat transfer packages, vacuum skid, exhaust fans, bathroom equipment and medical devices equipment.